May 20 2015. Cutting and Grading the Driveway

I've spent the past two days cutting the dirt out of the back of the property where the barn will be and moving the dirt by dump truck to the entrance driveway. I've been doing 6-8 inch lifts and compacting with the fully loaded dump truck...very effective compaction!
I still have a few more loads to go.





























Wednesday, May 13, 2015

051315 Cutting and filling

I spent the day cutting dirt out of the north side of the property and spreading it on the south side near the entrance to get the driveway up to grade and make room for the Barn It was cool (63F) and breezy with an onshore flow.















Tuesday, April 21, 2015

The Main Drains Are In 21/04/15

Todays progress included connecting the sewer pipe to the septic tank for the main house. This was a little tricky but turned out perfect. The upright pipe in the picture are 4" pipes as cleanouts connected to the 6" sewer pipe. All the septic piping is 6" diameter which will mean that they will be almost impossible to clog. The pipes for the drains are 4", 6" and 8" and connect to the grated drop boxes.





Thursday, April 2, 2015

Last Drain In 040215

Placed the last drain at the entrance of the property and moved some of the big rocks over to make room for the driveway.
Now I just need to connect the two front drains with 6" pipe.


                                     






Monday, March 30, 2015

An Update 03 29 15

The OWTS (Onsite Waste Treatment System) is complete and has passed inspection. The equipment vault is complete and is being finished on the inside. getting it ready for the installation of various contraptions to keep the structure warm, cold and amply supplied with water and electricity.
Here are some photos to update the progress: