The I beams are all in. Now for some formwork , galvanised roofing (verco w2) and some concrete.
Thursday, June 20, 2013
June 20 2013
I managed to get the I beams measured and drilled. I also sand blasted and painted one of them ready for placement.
Friday, June 14, 2013
June 14 2013
The concrete expansion bolts (1") are in...time to lower in the beams for hole fit up.
Saturday, June 8, 2013
June 8 2013
It was very foggy today (thick marine layer). I cut all the beams to the correct sizes using a combination of the plasma cutter, grinder and chop saw. Sand blasting painting and drilling is next.